We are in the process of getting ready for the final inspection. All misses, deficiencies, overspray and problems will be dealt with. We will be reviewing the cleaning of the inside of gutters as there seems to be lots that were missed. Once I finish my final inspection and deficiencies, we will ask Strata and home owners for deficiencies.
Greg
Operations
604-727-8918
Saturday, August 27, 2011
Friday, August 12, 2011
Update August 12th
Good weather has led to some excellent progress!
Building 5 is complete, pending final deficiencies.
Building 4 is complete, pending final deficiencies.
Building 3 is almost complete (90%).
Building 2 is nearing completion (75%).
Building 1 is nearing pressure washing completion, with paint prep work to begin shortly.
The small section of white lattice fencing on all buildings has not been painted; it will be coated on all buildings simultaneously at the end of the project.
-Operations