Friday, August 12, 2011

Update August 12th

Good weather has led to some excellent progress!

Building 5 is complete, pending final deficiencies.
Building 4 is complete, pending final deficiencies.
Building 3 is almost complete (90%).
Building 2 is nearing completion (75%).
Building 1 is nearing pressure washing completion, with paint prep work to begin shortly.

The small section of white lattice fencing on all buildings has not been painted; it will be coated on all buildings simultaneously at the end of the project.

-Operations