We are in the process of getting ready for the final inspection. All misses, deficiencies, overspray and problems will be dealt with. We will be reviewing the cleaning of the inside of gutters as there seems to be lots that were missed. Once I finish my final inspection and deficiencies, we will ask Strata and home owners for deficiencies.
Greg
Operations
604-727-8918
Saturday, August 27, 2011
Friday, August 12, 2011
Update August 12th
Good weather has led to some excellent progress!
Building 5 is complete, pending final deficiencies.
Building 4 is complete, pending final deficiencies.
Building 3 is almost complete (90%).
Building 2 is nearing completion (75%).
Building 1 is nearing pressure washing completion, with paint prep work to begin shortly.
The small section of white lattice fencing on all buildings has not been painted; it will be coated on all buildings simultaneously at the end of the project.
-Operations
Wednesday, July 27, 2011
Update July 27th
Building Five: Washing and majority of fascia painting is complete on building five, in progress on the rooftop fencing, hardy boards, and courtyard trellis fencing.
Building Four: Washing complete, prep and priming in progress, 1st coat paint has begun on areas prep has been completed.
Building Three: Washing complete on 75%.
Hopefully the good weather is here to stay!
-Operations
Saturday, July 16, 2011
Update July 16
Power washing is complete on building 5 and building 4 except for roof top decks which are being completed on Monday. Spot priming on undercover areas of building 5 have been completed. We will be washing building 3 starting on Monday. A review of rotten wood will be completed next week.
A sample of the main trim colour has been applied to building 5 in the North West corner unit column.
Greg
Operations
A sample of the main trim colour has been applied to building 5 in the North West corner unit column.
Greg
Operations
Monday, July 11, 2011
Update July 11th
It has started! Please say hello to Shawn and crew if you see them. We will be washing for the next four days.
Greg
Operations
Greg
Operations
Friday, July 8, 2011
Job Plan
We will be staring on building 5. The first order of business is to wash the whole building. After the building is washed, we start spot priming and painting. We will complete painting of the building before moving onto the next. We will start pressure washing the next building on rainy days. We will give at least 48 hours notice, if we are going to be washing your unit.
Greg
Operations
Start units 53-65 0n Monday
Wolfgang Commercial Painters will be pressure washing units 53-65 on Monday, July 11. We expect the pressure washing to take 4 days for these units.
We will be using a 15% bleach solution that will not be harmful to your plants.
We ask that you please close your windows during the pressure washing phase. We also request you remove all items from your deck and away from the exterior walls. All items that can’t be removed from the deck can be placed in the centre of the deck and covered to allow access to the exterior walls.
All Christmas lights and other items attached to the building must be removed to allow proper cleaning and painting.
Greg
Operations