Wednesday, July 27, 2011

Update July 27th

Building Five: Washing and majority of fascia painting is complete on building five, in progress on the rooftop fencing, hardy boards, and courtyard trellis fencing.
Building Four: Washing complete, prep and priming in progress, 1st coat paint has begun on areas prep has been completed.
Building Three: Washing complete on 75%.

Hopefully the good weather is here to stay!

-Operations